docs/projplan.txt

Sun, 10 Jul 2011 10:44:49 +0200

author
Michael Schloh von Bennewitz <michael@schloh.com>
date
Sun, 10 Jul 2011 10:44:49 +0200
changeset 11
f83d5d4b7088
permissions
-rw-r--r--

Modify icon to be square as most windowing systems expect icons to be.

     1    ____         _                   _      _   _  _
     2   / ___|   ___ | |__    __ _   ___ | |__  | | | || |__   _ __
     3   \___ \  / __|| '_ \  / _` | / __|| '_ \ | | | || '_ \ | '__|
     4    ___) || (__ | | | || (_| || (__ | | | || |_| || | | || |
     5   |____/  \___||_| |_| \__,_| \___||_| |_| \___/ |_| |_||_|
     7   Europalab SchachUhr - Game clock graphical user interface client
     9   PROJECT PLAN (IEEE 1058)
    11   Milestone release 1.2.0 (secondary enhancements)
    12     Due date: Dependent on code complete
    14   Milestone release 1.1.0 (primary enhancements)
    15     Due date: Dependent on code complete
    17   Milestone release 1.0.0 (testing complete)
    18     Due date: Dependent on design complete
    20   Milestone release 0.9.0 (code complete)
    21     Due date: Dependent on design complete
    22     Implemented requirements:
    23       Improve graphics, maybe replacing hand made SVGs with Wikimedia
    24       http://commons.wikimedia.org/wiki/Category:Chess_clocks
    25       Implement pausing of both subclocks midmatch (#B.01)
    26       Implement automatic update publication by RSS (#D.09)
    28   Milestone release 0.8.0 (documentation complete)
    29     Due date: Dependent on design complete
    30     Implemented requirements:
    31       Create mailing list and publicize on homepage.
    32       Write manpage and develop manpage generation framework.
    33       Write HTML online homepage and update URLs in AppUp and MeeGo.
    34       Publicize on Electrotrends and implement two article Google trick.
    36   Milestone genesis 0.7.0 (design complete)
    37     Due date: 20110810
    38     Achievements:
    39       Complete design specification and modelling.
    40       Give comparative consideration to competing projects.
    42   Milestone genesis 0.6.0 (prototype)
    43     Date: 20110708
    44       Complete requirements analysis.
    45       Produce a prototype in markup and script.
    46       Choose final implementation technologies.
    48   Milestone genesis 0.0.0 (project creation)
    49     Date: 20110702
    50       Search for similar competing projects.
    51       Create rough drafts of project guiding documents.
    52       Develop project structure and hosting environment.
    54   Unscheduled items
    55     See documents describing requirements and bugs.